We inform that we signed a construction of production hall for Comitor
Category of facility Production hall + office building
The total area of 2.073 m2 + 345 m2
Implementation year 2020 - 2021

The scope of work performer by the MCM Project:

a) the scope of executive design:
  • foundations of the hall and office building
  • structure of the hall
  • structure of the office building
  • roofing and wall cladding
b) the scope of work:
  • earthworks
  • buildings foundations
  • execution, delivery and assembly of hall steel structure
  • delivery and assembly of crane beams
  • delivery and assembly of roofing and wall cladding
  • delivery and assembly of hall equipment (gates, windows, doors, skylights, crane)
  • concrete flooring inside the hall
  • construction and finishing works of office building
  • land use
  • internal and external electrical installations
  • internal and External sanitary installations
  • post-completion documentation